How do you bring an RTM home to Saskatchewan?
Short answer
We build your house in Roseisle, Manitoba.
Professional movers bring it to your lot in Saskatchewan.
Your RM sets the permits, so start with a call to them.
Built in Roseisle. Delivered to your lot — no hassle.
Who does what?
We handle
The house, completely finished
- You usually handle
- The foundation, built while we build the house
We handle
Wiring and plumbing, stubbed through the floor
- You usually handle
- Permits from your RM
We handle
A full set of stamped plans
- You usually handle
- Septic, well and power hookups
We handle
Professional movers, with road permits and insurance
- You usually handle
- A firm, clear road into your lot
What does your RM ask for?
In Saskatchewan, building permits come from your local authority — your RM, town or city.
Under The Construction Codes Act, local authorities make building bylaws.
Those bylaws cover the placement and relocation of buildings, not only new construction.
Every RM writes its own rules. Two examples, from their own websites:
RM
Monet
- Worth knowing
- Lists RTMs and other houses moved onto a property as work that needs a permit. A development permit may also need a building permit. (RM of Monet)
RM
Edenwold
- Worth knowing
- Has its own move permit for moving a building to a place outside the RM: each RM sets its own rules. (RM of Edenwold)
Ask your RM three things:
- Which permits? Development, building, or both.
- What to send. Usually the house plans and a site plan. We give you a full set of stamped plans.
- Inspections. When they want to see the foundation.
Rules change. Check with your RM before you start.
How does the house travel on Saskatchewan roads?
Professional movers take care of the road permits and insurance.
In Saskatchewan, moving a building on a provincial highway needs a permit through SGI.
What that page says about timing:
No moves at night
Buildings are not moved between sunset and sunrise.
No weekend moves for wide loads
From 3:00 p.m. Friday to sunrise Monday; buildings under 7.32 m wide can move on Saturdays.
Quiet hours near cities
No travel within 25 km of major centres such as Regina and Saskatoon at rush hours and mealtimes.
So a long move is planned around the calendar, not just the distance.
What about septic and water?
Septic
A private sewage system needs a permit. The local public health inspector issues it and inspects the new system. (Private Sewage Works)
Well
A well driller builds it. Test the water before you move in.
See well and septic.

When does it all happen?
Order
You get stamped plans for your RM and your contractor.
Permits
Apply while we build the house.
Foundation
It goes in while we build.
Move day
About 6 months after you order. You move in at 7–8 months.
Your quote includes GST. No PST.
Where do we deliver in Saskatchewan?
Rated 4.9 ★ on Google.
Questions
Do you deliver RTM homes to Saskatchewan?
Yes. We build the house in Roseisle, Manitoba, and professional movers bring it to your lot in Saskatchewan. They take care of the road permits and insurance.
Do I need a permit to place an RTM home on my lot in Saskatchewan?
Usually, yes. Under The Construction Codes Act, local authorities set building bylaws that cover placing and relocating buildings. Some RMs list RTMs moved onto a property as work that needs a permit. Call your RM office first.
How long does an RTM home take for a Saskatchewan lot?
Delivery is about 6 months after you order. You move in at 7–8 months.
Who handles the septic in Saskatchewan?
You do, with a local installer. A private sewage system needs a permit, and the local public health inspector issues it and inspects the new system.